Earthworks, terracing and preparing of second phase of Asaluyeh petrochemical complex
Earthworks, terracing and preparing of second phase of Asaluyeh petrochemical complex
-
|
Category:Earthworks - Road construction
|
-
|
Client:شرکت مدیریت توسعه صنایع پتروشیمی
|
-
|
Consultant:Sazeh Pardazi Iran Consulting Engineers
|
-
-
-
|
Initial Price:5.500.000 $
|
-
-
Explosive digging operations and chipping for 3.500.000 square meters.
Digging and embanking operation implementation with leveling and tuning up has been done in order to prepare the structure for submission to the different companies throughout the second petrochemical phase in Asaluyeh. This phase includes 3.500.000 square meters of excavation undertaken through explosions, chipping and bulldozing. The value of this project has been 55 billion Rials.